San Luong dwelling area
Total area: 8000 m2
Including: building plots, garden houses and land for greenery & sport
110 kV overhead line connecting Nam Chim 1 & 1A HPP complex with 110 kV Substation for Mai Son cement plant (32 kms)
110 kV overhead line connecting Nam Chim 1 & 1A HPP complex with 110 kV Substation for Mai Son cement plant (32 kms)
Nam Chim 1A hydropower project
Nam Chim 1A hydropower project (2x5MW), type: horizontal Francis turbine supplied by Andritz Hydro Pvt. Ltd. (India).
110 kV Substation for Mai Son cement plant
110 kV Substation for Mai Son cement plant, initiated in April 2006 and operated in April 2010
Nam Chim 1 hydropower project
Capacity: 2x8MW, type: horizontal Pelton turbine supplied by Tata International Ltd. (India), make: Jyoti Ltd.
Started in 06/2006 and put into operation in 04/2010